Release Report Of Bridge Records Delay: Expert

"); jQuery("#212 h3").html("

Related News Programmes

"); });

2019-02-11 HKT 15:54

Share this story

facebook

  • Release report of bridge records delay: expert

A veteran engineer has called on the government to release a report submitted by an independent consultant about a delay in submitting key construction documents related to a section of the Hong Kong-Zhuhai-Macau Bridge.

Albert Lai from the Professional Commons think tank said publication of the report is essential to enhance transparency and reassure the public.

The Highways Department had hired the consultant after finding that about 10,000 documents were not submitted on time by China State Construction Engineering for the project involving a section of road between Scenic Hill and the Hong Kong Boundary Crossing Facilities.

Highways officials said they were notified by the consultant, Arup, in July – just a few months before the opening of the bridge – that the contractor failed to submit about 10,000 Request for Inspection and Survey Checking (RISC) forms.

Officials said the contractor had now submitted the forms, with the dates of the signatures indicating a late submission.

In its note on Sunday, the Highways Department had said that the matter does not involve quality issues and said an independent consultant it had hired had gone through all the records. It said no forgery of documents was found.

Lai said it "defies" logic that the report of this late submission only surfaced last summer.

"These forms should have been filled up at the time of the inspection, with multiple copies kept by the contractor and the engineers as well as the Highways Department," he said.

The delay indicates serious issues in monitoring, Lai said.

But a former director of civil engineering and development, Raymond Chan, said whether engineers filled in the forms on time or not is not the key issue, as long as proper site supervision was carried out.

He said engineers could sign the forms after they had returned to their offices, as the conditions at work sites are not always good.

Civic Party lawmaker Tanya Chan said a two-year delay in submitting the records was not acceptable, and the government should consider whether to punish the construction company in question.

She said the government should also bring in new rules to make sure companies hand in documents required on time.

RECENT NEWS

SBI Holdings To Acquire Bitbank In US$289M Crypto Expansion

SBI Holdings has agreed to acquire Japanese crypto exchange Bitbank in a deal valued at approximately US$289 million, w... Read more

4 Ways Hong Kong Banks Fight Financial Crime Using AI, According To HKMA

The Hong Kong Monetary Authority (HKMA) wants banks to use AI in financial crime as a way to counter cyberattacks and s... Read more

Ripple Launches RLUSD Stablecoin In Japan Through SBI Group

Ripple has launched its US dollar-denominated stablecoin, Ripple USD, in the Japanese market. The expansion follows reg... Read more

SBI And Startale Launch Trust Bank-Backed Yen Stablecoin JPYSC In Japan

SBI Group has introduced its trust based stablecoin JPYSC in partnership with Singapore-based fintech company Startale ... Read more

Visa Study: Digital Wallets Lead Greater Bay Area Payment Preferences

Visa has released its latest Consumer Payment Attitudes Study, highlighting how payment seamlessness is linked to a shi... Read more

European And South Korean Banks Form Project Pangea For FX Settlement

Chainlink, South Korean infrastructure provider FairSquareLab, the Unified Korea Alliance (UniKA), and European stablec... Read more