Release Report Of Bridge Records Delay: Expert

"); jQuery("#212 h3").html("

"); });
2019-02-11 HKT 15:54
A veteran engineer has called on the government to release a report submitted by an independent consultant about a delay in submitting key construction documents related to a section of the Hong Kong-Zhuhai-Macau Bridge.
Albert Lai from the Professional Commons think tank said publication of the report is essential to enhance transparency and reassure the public.
The Highways Department had hired the consultant after finding that about 10,000 documents were not submitted on time by China State Construction Engineering for the project involving a section of road between Scenic Hill and the Hong Kong Boundary Crossing Facilities.
Highways officials said they were notified by the consultant, Arup, in July – just a few months before the opening of the bridge – that the contractor failed to submit about 10,000 Request for Inspection and Survey Checking (RISC) forms.
Officials said the contractor had now submitted the forms, with the dates of the signatures indicating a late submission.
In its note on Sunday, the Highways Department had said that the matter does not involve quality issues and said an independent consultant it had hired had gone through all the records. It said no forgery of documents was found.
Lai said it "defies" logic that the report of this late submission only surfaced last summer.
"These forms should have been filled up at the time of the inspection, with multiple copies kept by the contractor and the engineers as well as the Highways Department," he said.
The delay indicates serious issues in monitoring, Lai said.
But a former director of civil engineering and development, Raymond Chan, said whether engineers filled in the forms on time or not is not the key issue, as long as proper site supervision was carried out.
He said engineers could sign the forms after they had returned to their offices, as the conditions at work sites are not always good.
Civic Party lawmaker Tanya Chan said a two-year delay in submitting the records was not acceptable, and the government should consider whether to punish the construction company in question.
She said the government should also bring in new rules to make sure companies hand in documents required on time.
TOPPAN Edge And Partisia Partner For Fully Privacy-Focused Digital Identity Solution
TOPPAN Edge is partnering with Partisia to develop a fully privacy-focused digital identity using Partisia’s Decentr... Read more
Livi Bank Achieves HKD2.9B In Customer Deposit Growth
livi Bank reported a total operating income of HK$220 million in 2024 in its latest annual report results, marking a 76... Read more
OSL And Ant Digital Partner To Drive Real-World Asset Tokenisation
OSL Group (863.HK), a publicly listed company for digital assets, and Ant Digital Technologies signed a Memorandum of U... Read more
WeLab Bank Hits Profit In 2025 With HKD750M Revenue
WeLab Bank achieved profitability in Q1 2025*, continuing from 2024 when it achieved breakeven within four years of its... Read more
Adoption Of GenAI Rises In Hong Kongs Financial Sector, Though Focus Remains On Internal Operations
In Hong Kong, financial institutions are increasingly adopting generative artificial intelligence (genAI), aiming for e... Read more
HKMA Forms CargoX Expert Panel To Modernise Trade Finance
On 28 April 2025, the Hong Kong Monetary Authority (HKMA) announced the creation of an Expert Panel on Project Cargox. ... Read more