Leighton To Blame For Missing Documents: MTRC
"); jQuery("#212 h3").html("

"); jQuery(document).ready(function() { jwplayer.key='EKOtdBrvhiKxeOU807UIF56TaHWapYjKnFiG7ipl3gw='; var playerInstance = jwplayer("jquery_jwplayer_1"); playerInstance.setup({ file: "https://newsstatic.rthk.hk/audios/mfile_1440765_1_20190130194657.mp3", skin: { url: location.href.split('/', 4).join('/') + '/jwplayer/skin/rthk/five.css', name: 'five' }, hlshtml: true, width: "100%", height: 30, wmode: 'transparent', primary: navigator.userAgent.indexOf("Trident")>-1 ? "flash" : "html5", events: { onPlay: function(event) { dcsMultiTrack('DCS.dcsuri', 'https://news.rthk.hk/rthk/en/component/k2/1440765-20190130.mp3', 'WT.ti', ' Audio at newsfeed', 'WT.cg_n', '#rthknews', 'WT.cg_s', 'Multimedia','WT.es','https://news.rthk.hk/rthk/en/component/k2/1440765-20190130.htm', 'DCS.dcsqry', '' ); } } }); }); });
2019-01-30 HKT 19:46
The MTR Corporation has blamed its contractor Leighton for a new set of construction problems at its Hung Hom station, saying it’s ‘extremely disappointed’ in the company and reserves the right to take legal action.
Speaking to the media after the government revealed that as much as 40 percent of key construction documents, known as ‘Request for Inspection and Survey Checks forms’ (RISC) have gone missing, the railway firm’s CEO Lincoln Leong placed the blame squarely on the contractor.
“The records, the so-called RISC forms should originate firstly from Leighton. We have been asking them and chasing them for as many of the RISC forms as they have, and we’ve been asking them for a number of months”, Leong said.
He said these forms are crucial evidence to prove that the works conform to approved designs, and the railway only received from Leighton ‘as-constructed’ drawings of what was built at two approach tunnels and a secondary track in December.
It was only after MTR officials combed through these drawings that they realised that Leighton had changed the approved design for some reinforcement bars at the tunnels, and that many documents were missing, Leung said.
“I myself will not believe that we’ll be able to find these missing forms”, he admitted.
But Leung stressed that the alteration – changing ‘lapped’ rebars to ones that are fixed to couplers – are relatively common in complex projects, and “there is currently no evidence or sign of any structural issues that may raise any concerns regarding the safety of these structures.”
He added that these are ‘simple’ structures that rest mainly on solid ground, and trains have been using the tunnels as part of tests of the station extension without any problems.
But Leong couldn’t say whether the new revelations will cause further delays to the opening of the Shatin-to-Central line, saying only that the rail firm will focus on finding the missing documentation, and will work with the government on how to proceed.
Leong didn’t explain why the MTRC didn’t realise the problem earlier, because the railway is supposed to sign off on these RISC after inspecting the construction works. He would only say that the railway didn’t do a good job in overseeing the project.
“We ourselves at MTR should have done better in ensuring the completeness of necessary documentation. This is an improvement which we need to make”, Leong said.
The MTR is also under fire for apparently inaccurate tests it has been conducting on the problem-plagued platforms of the same station.
For over a month, staff have been using an ultrasound machine to test whether steel rebars are properly screwed into couplers, after allegations that the bars were systematically cut short, and installed improperly.
But on Wednesday, it was revealed at a Commission of Inquiry that physical examinations of several bars conducted by the police – after they were cut out of the cement – revealed that the ultrasound measurements were significantly off.
The MTR's Divisional General Manager for Projects, James Chow, said they’d had extensive discussions with government experts on the methodology of the non-destructive tests when coming up with this ultrasound method.
He said they are now following up with officials on why the ultrasound results differ so much from the physical examinations, and tests originally scheduled for Thursday have been cancelled as a result.
XTransfer Celebrates Milestone Of Over 1 Million Enterprise Clients
XTransfer shared that it has served more than one million enterprise clients since its founding in 2017. The B2B cross-... Read more
How Much Do Hong Kongs Biggest Banks Pay Their CEOs?
How much did it pay to run one of Hong Kong’s biggest banks in 2025? The answer varies sharply, and the numbers look ... Read more
DBS Hong Kong CEO Sebastian Paredes To Retire After 16 Years, Taiwan Chief Takes Over
Ng Sier Han will be the next DBS Hong Kong CEO. He takes over from Sebastian Paredes, who retires from executive duties... Read more
Hong Kong Founders Can Now Incorporate And Get Paid In One Application
Airwallex announced a corporate partnership with Air Corporate, a Hong Kong-based digital corporate service provider, i... Read more
Visa Tap To Pay Reaches Hong Kong Doorsteps In SF Express Deal
Visa announced a partnership with S.F. Express (Hong Kong) Limited (SFHK) to bring contactless card payment services to... Read more
Two Co-CEOs Take Over HSBC Insurance Leadership As Edward Moncreiffe Exits
HSBC has named two Asia-based executives as co-CEOs of its global insurance business. Daisy Tsang, CEO of HSBC Life Hon... Read more